The ratio of the efficiencies of A, B and C is 2 : 5 : 3. Working together, they can complete a work in 27 days. B and C together can complete 4/9th part of that work in :

Questions :

The ratio of the efficiencies of A, B and C is 2 : 5 : 3. Working together, they can complete a work in 27 days. B and C together can complete 4/9th part of that work in :

Options :

  • 27 days
  • 15 days
  • 17 1/2 days
  • 24 days

correct answer : b)